HS2 Delta Junction: October's Bridge Launch And An 11-Metre Wall

Nov 03, 2026

Leave a message

David Smith
David Smith
David is a senior designer at Shaanxi Flourish Industrial Co., Ltd. With over 10 years of experience in the construction equipment design field, he is responsible for creating innovative building templates and formwork systems. His designs have been widely used in various residential, commercial, and industrial projects.

Two structures now cross the M6 side by side, the second launched in October. A third - a wall - went up alongside them, and the wall is the part to read twice.

The 4,750-tonne push

On Saturday 24 October 2026, HS2 pushed the last section of its second M6 viaduct over both carriageways at junction 4/4a, near Chelmsley Wood. Traffic kept running underneath. The structure weighs 4,750 tonnes.

Both M6 South viaducts are now structurally complete: the east deck finished in 2025 and runs towards Euston, the west deck faces Curzon Street and destinations in the north. Each is 320 metres long and sits 100 millimetres from its twin - a tolerance, not a drawing accident. Both are weathering steel on concrete piers.

Site constraints meant the two decks were assembled and launched differently: four incremental pushes west, three east. Each launch added steel sections to the rear and moved the deck on strand jacks. By the final push the deck rested on the piers either side of the carriageway, which let it travel with traffic live below.

That last push took nine hours and moved the deck 76 metres. HS2 also gives an average speed of twelve metres per hour, and twelve times nine is 108, not 76. Those three figures do not reconcile, so quote the distance or the rate, not both.

The M42–M6 link road closed as a safety exclusion zone and reopened 25 hours early, at 9pm on the Saturday. Ian Clarke of HS2 Ltd said the bridges cross some of the busiest motorway in the country, which is why the programme avoids closing lanes where it can.

The window that moved

The same weekend, weather made a decision. Water Orton's parapet work over the M42 was booked for 23–26 October. With strong winds forecast across large parts of the UK, HS2 postponed it, kept J6–9 northbound and J9–7 southbound open, and moved it to 9pm Friday 30 October through 5am Monday 2 November.

That is the routine cost of building over a live motorway. HS2's works page logs five M42/M6 closures from late June to September 2026, all complete. The Water Orton spans were assembled beside the road and rolled in on self-propelled modular transporters.

What a launch takes away

Launching and SPMT delivery move work off the ground and off the critical path. HS2 says so: launching reduces the need for extensive ground-based scaffolding.

Read that as a trade. Fewer falsework towers under a bridge means the load went elsewhere - into permanent piers, launch bearings, the strand-jack reaction frame, and the casting yard. What leaves the elevation returns as tolerances: bearing alignment, jack synchronisation, and the stiffness of the temporary support halfway across.

Delta Junction is that trade at scale: thirteen viaducts over motorways, roads, rail and floodplains. Its concrete decks use segments from the Kingsbury yard; piers were cast in situ on piles. The formwork risk moved with them, out of the falsework under the bridge and into the pier and foundation pours.

The 11-metre wall

Inside the same junction is the Birmingham Spur Dive-Under: a 400-metre-long, 11-metre-high concrete box that lets one HS2 line pass under another instead of crossing at grade. Balfour Beatty VINCI is building it. PERI UK supplied scaffolding, formwork and accessories as one package.

Eleven metres is the number that decides the formwork. For those pours BBV used PERI's VARIO girder wall formwork, a component system that let engineers close up girder, waler and tie spacing to carry the higher pressure from taller lifts.

That is the commercial meaning of high wall formwork, stated plain. A taller wall rarely needs a stronger panel; it needs a denser arrangement of the same parts. More girders per square metre, walers at closer vertical centres, ties on a smaller grid. The face is seldom the governing item. The spacing is.

Access follows the same logic. PERI UP Flex gave rebar crews a platform on the 11-metre walls; the scaffold and formwork designs were coordinated in-house before either reached site.

At roof level the problem changes shape. PERI's SCS brackets anchor into the finished 11-metre walls to form a high-level platform, which removes ground support and stops tie rods passing through concrete that is already complete.

Dan Biggs, senior sales engineer at PERI UK, put it commercially: the customer does not want accessories, scaffolding and formwork from three suppliers. Discount the sales language; a scaffold-formwork clash is a drawing-stage problem, cheaper to fix on paper than at the eleventh metre.

The pressure on the drawing

ScaffMag's October report adds a detail PERI's project page does not carry: pressure sensors went onto selected wall pours, so the team could read formwork load in real time against the design-stage pressures.

There is a reason to pay for it: lateral pressure from fresh concrete is not a property of wall height, but an output of how the concrete is placed.

In UK practice the design route is CIRIA Report 108, with BS 5975 covering temporary-works procedure; in North America it is ACI 347. Both cap pressure at full hydrostatic and tie the maximum to placement rate, temperature, mix and section size.

Run CIRIA's expression on an 11-metre wall at 25 kN/m³ and the hydrostatic ceiling is 275 kN/m². Nobody designs to that. Take ordinary Portland cement concrete without retarder at 15 °C and the predicted maximum moves with pour rate - about 57 kN/m² at one metre per hour, 67 at two, 80 at four, 91 at six.

Those are our substitutions into the published expression, not site measurements: C1 1.0 for a flat wall, C2 0.3 for ordinary Portland cement, 25 kN/m³, 15 °C. Going 1 to 2 m/h lifts the load 17 per cent; 2 to 4 m/h another 21.

Then the site variables. A pump faster than the design rate raises pressure. A wetter mix behaves closer to a fluid and sets later. Internal vibration fluidises concrete locally and lifts pressure at the vibrated depth. Cold concrete sets slower, so a winter pour loads harder than the same mix in July.

A design pressure is a prediction about a method, and the method is decided on site. That is what the sensors were checking, and why a tall wall deserves monitoring as well as calculation.

Where a catalogue has to line up

None of the above is about buying a heavier panel. The useful questions on a tall wall are about centres.

Our Q700 concrete wall formwork system is built on that reading: a 1.5 mm Zn-Al-Mg coated face on 2 mm edge plate, Q700 substrate yielding above 700 MPa, seven panel widths from 100 to 400 mm and around 25 kg/m² (both factory confirmation required), 1500+ hours salt spray.

Higher yield buys margin when the tie grid opens out; low weight buys handling speed on a wall where every lift is a climb.

The tie grid is set at the waler. Our square tube waler for the Q700 system runs Q235 or Q355 rectangular hollow sections, 50×30 to 80×30 mm with 2.0–3.0 mm walls, doubled across the panel back, with long slots so the tie bolt slides to each panel's layout instead of being drilled on site.

Ties carry what the walers collect. Our tie-rod formwork panel has Φ16 and Φ18 mm tie holes pre-punched at fixed centres, in four modules covering 300 and 500 mm widths and 1200 and 2400 mm lengths, clamped with wall-through bolts, tie plates and plastic cone nuts from one supplier.

Where there is no room on the far side, triangular truss single-side wall formwork carries the pressure through a factory-welded steel channel and punched-angle truss with embedded base anchors: no tie rods through the wall, one-pass pours of 3 to 7.5 metres, truss spacing between 750 and 900 mm. No tie holes means no sealing and no water path afterwards.

None of that is a claim about HS2. It is the same argument at a smaller scale: the arrangement carries the load, and it is chosen against a placement method you can hold on site.

Before you price the next tall wall

Four questions, in the order that decides the money.

  • What placement rate is the design pressure based on, and can the pump hold it? Put the rate in the pour plan, not just the calculation.
  • What slump is specified at discharge, and who checks it at the pump? A mix arriving wetter than the assumption voids the pressure figure.
  • Do scaffold and formwork occupy the same space, and has anyone checked before mobilisation? The Dive-Under package was coordinated at design stage for that reason.
  • What happens to the platform when the pour reaches the top? If the answer is ground support or ties through finished concrete, revisit access before the wall, not after.

The M6 decks will be remembered for the launch. The wall is the part that repeats - and the part where a supplier's catalogue, a designer's assumption and a pump operator's actual rate have to agree.