Can Shoring Props Stay in Place? Temporary versus Permanent Use

Nov 23, 2026

Leave a message

Telescopic steel props are temporary works. They are designed, tested and certified for the construction period, and the standards that cover them - EN 1065 for the prop, EN 12812 for the falsework it belongs to - say nothing about a fifty-year service life. Leaving one in place permanently is not a matter of adding a coat of paint.

There are projects where props are legitimately left behind, and this article covers what those require. But the starting point has to be clear: a standard EN 1065 prop is a temporary component, and permanent support is a different design task.

Shoring Putlog Coupler suppliersScaffolding Base Jack best

Two different systems share the word "shoring"

A great deal of confusion in this subject comes from using one word for two unrelated systems. They are not interchangeable and their standards do not overlap.

  Vertical shoring / falsework Excavation support
What it does Holds up formwork and fresh concrete from below Holds back soil at a trench or basement dig
Load Vertical, gravity Horizontal, earth pressure and surcharge
Typical components Props, frames, ringlock towers, beams, U-heads Sheet piles, trench boxes, struts, anchors, walers
Governing standards EN 1065, EN 12812, BS 5975, ACI 347 EN 1997-1, local excavation and trench safety rules

Props and prop accessories belong to the first column only. A ringlock ledger or a swivel coupler has no role in holding back soil, and a trench box has no role under a slab.

What EN 1065 actually certifies

EN 1065 covers adjustable telescopic steel props and classifies them A to E by characteristic resistance, from 20 kN up to 40 kN. The test regime is a short-duration load test to a defined deformation limit, plus checks on the pin, the thread and the base plate.

What the standard does not do is equally important:

  • It does not assess behaviour under sustained load for decades.
  • It does not require a corrosion allowance for a design life beyond the construction period.
  • It does not address fire resistance.
  • It does not address loosening of the pin or the adjusting nut under repeated thermal or dynamic movement.

Those four gaps are precisely the failure modes of a prop left in place.

Why a temporary prop fails as a permanent one

Corrosion at the details, not on the surface. Hot-dip galvanising to EN ISO 1461 gives about 70 µm average. On an exposed flat face in a C3 environment that is a loss rate near 0.7 µm per year, which sounds adequate for 50 years. But the inner tube is not galvanised after assembly, the thread flanks are thin, and the pin holes are cut after coating. Those are the points where section loss starts, and none of them is inspectable in service.

Loosening. A prop carries load through a pin in a hole and a nut on a coarse thread. Both are clearance fits. Over a construction period of weeks, that is irrelevant. Over years of thermal cycling and floor vibration, the nut walks and the pin frets. There is no locking device on a standard prop because the standard assumes the load is temporary.

Fire. A permanent steel member in a building has to achieve a fire resistance period, typically R30 to R90, either by section factor or by protection. A 3 mm wall prop with no protection reaches critical temperature in minutes. Temporary works are not required to satisfy this because nobody occupies the building while they are in service.

Sustained load. Concrete creeps and shrinks; a prop left under load attracts more of it as the surrounding structure creeps. The load path in a permanent structure is analysed for that redistribution. A prop pinned between a slab and a floor was not.

Temporary versus permanent, side by side

Requirement Temporary (EN 1065 / EN 12812) Permanent (EN 1993 / EN 1992)
Design working life Construction period, typically under 12 months 50 years
Load combination Construction dead + live + impact Permanent + variable + wind + seismic + thermal
Corrosion protection Galvanised to EN ISO 1461 Coating system to EN ISO 12944 for the corrosivity category, often 200 µm or thicker, or a calculated corrosion allowance
Fire Not required R30–R90 by calculation or protection
Connections Pin and thread, adjustable, no locking Welded or preloaded bolted, against loosening
Verification Product standard plus falsework design check Structural calculation, permit review, inspection regime

The case where props really are left in

It happens, particularly in refurbishment and in temporary works that become inaccessible. The legitimate route has four steps, and all four are usually required:

  1. Re-analyse. The prop is removed from the temporary load case and added to the permanent one, with sustained-load factors and the creep redistribution that follows.
  2. Reduce the resistance. Apply a corrosion allowance to the measured wall thickness, and take the buckling length as the full unbraced height rather than the falsework design value.
  3. Deal with fire and durability. Either protect the member, or demonstrate that the compartment does not require it to perform in fire.
  4. Record it. As-built drawings, the calculation, and an inspection schedule. A prop that nobody knows is structural is the worst outcome of all - a later fit-out contractor will cut it out without a second thought.

Where the answer to step 2 or 3 is unfavourable - which is common - the cheaper solution is usually to replace the prop with a purpose-made steel column or a concrete encasement, and remove it from the permanent load path entirely.

What to ask a supplier

  • Which EN 1065 class, and what characteristic resistance that corresponds to (class D is 30 kN, class E is 40 kN).
  • The galvanising thickness test report, and whether the inner tube is coated.
  • Whether the nut has any anti-loosening feature.
  • Whether a design check to EN 1993 for permanent use is available. Most manufacturers will say no, because the product was never assessed for it.

For the capacity side of the temporary design - how many props, at what grid, under what slab thickness - the tables in formwork shoring load capacity apply directly. The props themselves are here: shoring props, with the matching base jack and U-head - the two components that decide whether the load actually gets into the prop in the first place.

Questions that come up at enquiry stage

Can I use shoring props as permanent columns?

Not a standard EN 1065 prop, no. It has no corrosion allowance at the threads and pin holes, no locking device, no fire performance and no sustained-load verification. A permanent column has to be designed as one, to EN 1993, and will normally be a welded or bolted section rather than a telescopic prop.

What if the prop will be buried or inaccessible?

Then the permanent route is mandatory rather than optional, because it can never be inspected again. In practice that means encasing it, or replacing it with a designed member before the void is closed.

How long can a temporary prop stay in place?

As long as the falsework design says, and the design should state a period. Backpropping under a multi-storey slab is normally removed within weeks of the concrete reaching transfer strength. Leaving props under load for months is a scheduling decision that should be checked against the design, not assumed.